Edit

Town Of Dedham Public Safety Building - What's Happening December 27, 2022 To December 30, 2022

Government and Politics

December 26, 2022

From: Town Of Dedham

Project Overview:

Construction of a combined public safety building commenced in December 2020 on the site of the former Town Hall at 26 Bryant Street. The new building will house the staff and equipment of Fire, Police, and Dispatch departments. The new combined Public Safety Building will replace two older Town buildings: Police Station at 600 High Street (built in 1962) and the Fire Station at 436 Washington Street (built in 1930). The new building is scheduled to open in the Winter of 2022.

livestream video of the construction is available on the Project website! Tune in from anywhere to watch the continued progress on the Combined Public Safety Building. While there, check out the updated Before-and-After photos of the progress onsite.

What to expect December 27, 2022 (Tuesday) through December 30, 2022 (Friday):

The project site remains closed to the public.

The site will remain closed this weekend through Monday, December 26, 2022. Work will resume at 7AM on Tuesday, December 27, 2022.

Plumbers will install finishes in the women’s locker room and within the Chief’s bathroom.

Sheet metal contractors will relocate the cabinet unit heater within the lobby vestibule and will perform remaining punch list repairs.

Painters will finish touch-ups throughout the building.

Fire protection system and sprinkler system training successfully completed on December 21, 2022.

Electricians will continue to pull wires within the apparatus bay and for devices installed on the first floor.

Miscellaneous Metals Contractor will be working within Stair #2 and has completed the installation of the fire pole in both stairs.

Fencing contractor will install security enclosures within the basement.

Concrete subcontractor will continue concrete repairs at the openings to the two stairs and will perform repairs along the north apron of the building.

Expect periodic entrance and exit of large trucks at the project site entrance, located at the intersection of Washington Street and Bryant Street.Please expect minor traffic delays at this intersection.

No additional traffic impacts or pedestrian impacts are anticipated during this week.

Public Viewing Area:

If you want to stop by to check out the progress, stand by the picnic table outside the north entrance to Town Hall. This spot provides a great view into the project site and is outside of the project boundaries. Worth a visit!

Construction Hours:

Crews will be onsite:

Tuesday through Friday: 7:00 AM to 5:00 PM

Project Team Contact Information:

Immediate issues or concerns, please contact the Town Manager’s Office at 781-751-9100.

For general questions or concerns, please contact the project team at [email protected]

For more information about the Public Safety Building Project, please visit the project website atwww.dedham-ma.gov/psb

Download ourproject team contact information flyeron the project website.

Click on the images below to enlarge

Photo from the top of the slide pole on the second floor of the Fire Department looking down to the base on the first floor, taken on Wednesday, December 21, 2022.

Caption: Photo from the top of the slide pole on the second floor of the Fire Department looking down to the base on the first floor, taken on Wednesday, December 21, 2022.

Photo of the active construction site facing the south side of the building at the new public entrance, taken on Wednesday, December 21, 2022. Crews have completed the parking lot striping to show the two lanes of travel and visitor parking spaces adjacent to the lined crosswalk.

Caption: Photo of the active construction site facing the south side of the building at the new public entrance, taken on Wednesday, December 21, 2022. Crews have completed the parking lot striping to show the two lanes of travel and visitor parking spaces adjacent to the lined crosswal

Click Here For More Information