Town Of Dedham : Public Safety Building - What's Happening December 5, 2022 To December 9, 2022

Government and Politics

December 5, 2022

From: Town Of Dedham

Here is a look-ahead at the construction work planned for the Public Safety Building, from December 5, 2022 to December 9, 2022

Project Overview:

Construction of a combined public safety building commenced in December 2020 on the site of the former Town Hall at 26 Bryant Street. The new building will house the staff and equipment of Fire, Police, and Dispatch departments. The new combined Public Safety Building will replace two older Town buildings: Police Station at 600 High Street (built in 1962) and the Fire Station at 436 Washington Street (built in 1930). The new building is scheduled to open in the Fall of 2022.

livestream video of the construction is available on the Project website! Tune in from anywhere to watch the continued progress on the Combined Public Safety Building. While there, check out the updated Before-and-After photos of the progress onsite.

What to expect December 5, 2022 (Monday) through December 9, 2022 (Friday):

The project site remains closed to the public.

Weekend Work:Contractors will be working onsite onSaturday, December 3, 2022,between 8:00 AM and 4:00 PM.

HVAC contractors will continue repairing insulation fittings, install rough-in piping to manifolds, and will install a split system in the decontamination area.

Sheet metal contractors will install an exhaust within the basement locker area.

Plumbing contractors will install finishes within the basement area.

Electricians will continue to pull wires within the apparatus bay and install fire alarms in the stairwells.

Painting in the Sallyport area will be substantially complete this week.

Masons will be onsite to finish grouting around the cell block doors and will address remaining punch list items.

Concrete subcontractors will be forming sidewalks along Bryant Street.

Site contractors will continue backfilling areas within the project boundaries along the west, and will instill granite curbing.

Acoustic contractors will finish installing the wood ceiling panels within the lobby at the public entrance.

Installer will continue the installation of the new overhead doors within the Apparatus Bay.

Landscapers will continue installing new stone pavers along the exterior of the west side of the building.

Expect periodic entrance and exit of large trucks at the project site entrance, located at the intersection of Washington Street and Bryant Street.Please expect minor traffic delays at this intersection.

No additional traffic impacts or pedestrian impacts are anticipated during this week.

Public Viewing Area:

If you want to stop by to check out the progress, stand by the picnic table outside the north entrance to Town Hall. This spot provides a great view into the project site and is outside of the project boundaries. Worth a visit!

Construction Hours:

Crews will be onsite:

Saturday, December 3, 2022: 8:00 AM to 4:00 PM

Monday through Friday: 7:00 AM to 5:00 PM

Project Team Contact Information:

Immediate issues or concerns, please contact the Town Manager’s Office at 781-751-9100.

For general questions or concerns, please contact the project team at[email protected]

For more information about the Public Safety Building Project, please visit the project website atwww.dedham-ma.gov/psb

Download ourproject team contact information flyeron the project website.

Click here for more information