Town Of Dedham Public Safety Building - What's Happening February 6, 2023 To February 10, 2023

Government and Politics

February 6, 2023

From: Town Of Dedham

Here is a look-ahead at the construction work planned for the Public Safety Building, from February 6, 2023 to February 10, 2023

Project Overview:

Construction of a combined public safety building commenced in December 2020 on the site of the former Town Hall at 26 Bryant Street. The new building will house the staff and equipment of Fire, Police, and Dispatch departments. The new combined Public Safety Building will replace two older Town buildings: Police Station at 600 High Street (built in 1962) and the Fire Station at 436 Washington Street (built in 1952). The new building is scheduled to open in early 2023 with final completion later this year.

Moving to the New Building

The anticipated move-in date is still March 3, 2023 and will begin with the Fire Department. The project remains on budget.

Additional updates and information will be shared when available on the project page (www.dedham-ma.gov/psb) and will be shared via email. Subscribe at www.dedham-ma.gov/subscribe and select “Public Safety Building” from the list of news topics.

A Live View of the Project

A livestream video of the construction is available on the Project website! Tune in from anywhere to watch the continued progress on the Combined Public Safety Building. While there, check out the updated Before-and-After photos of the progress onsite.

What to expect February 6, 2023 (Monday) through February 10, 2023 (Friday):

The project site remains closed to the public.
Members of the project team and Town IT Department will be onsite tomorrow, Saturday, February 4, 2023, between 8AM and 4PM.
HVAC crews will be onsite to perform systems testing and will insulate valves within the induction units.
Electricians will be onsite this week to run power to the lockers on the second floor of the Fire Department, label jacks throughout the building, and will run through remaining punch list items.
Miscellaneous Metals contractors will be onsite to grind and smooth stainless steel elbows on both stairwells, and will install a stainless steel rail along the Detention Corridor.
Contractors will install remaining door hardware throughout the building.
The installation of the rubber flooring on stairwell #1 is nearing completion and will continue this week.
Remaining window blinds will be installed throughout the building.
Site fencing will continue to be installed this week around the exterior of the building.
Crews will finish cleaning the Apparatus Bay floors.
Expect periodic entrance and exit of large trucks at the project site entrance, located at the intersection of Washington Street and Bryant Street. Please expect minor traffic delays at this intersection.
No additional traffic impacts or pedestrian impacts are anticipated during this week.

Public Viewing Area:

If you want to stop by to check out the progress, stand by the picnic table outside the north entrance to Town Hall. This spot provides a great view into the project site and is outside of the project boundaries. Worth a visit!

Construction Hours:

Crews will be onsite:
Saturday, February 4, 2023: 8:00 AM to 4:00 PM
Monday through Friday: 7:00 AM to 5:00 PM

Project Team Contact Information:

Immediate issues or concerns, please contact the Town Manager’s Office at 781-751-9100.
For general questions or concerns, please contact the project team at [email protected]
For more information about the Public Safety Building Project, please visit the project website at www.dedham-ma.gov/psb
Download our project team contact information flyer on the project website.