From: Town Of ArlingtonArlington HS Construction Schedule: April 2020 – September 2025
Construction Look Ahead – Week of February 27th, 2023
The above diagram covers all work to be performed during the current phase. Specific work to be performed this week includes:
Public Way Impacts:
• Deliveries ongoing
General Site Activities:
• Phase 2:
o Steel fireproofing
o Steel detailing
o Installation of skylights
o Installation of stairwells
o Layout for overhead M/E/P
o Exterior and interior framing
o Install overhead mechanical, plumbing, and fire sprinklers
o Installation of roofing system
o Installation of elevator shaft
o Dust mitigation ongoing
• Material Stockpile/Temp Construction Lot:
o Contractor storage and parking
• Schouler Court:
o Construction vehicles entering and exiting project site
Weekend Work/Holiday Work/Night Work:
• Saturday work is required for the foreseeable future