Pima County : Sewer Work For The Week OfFebruary 27-March 3, 2023

Government and Politics

February 24, 2023

From: Pima County Government

The Pima County Regional Wastewater Reclamation Department and its contractors will conduct sewer repairs at the following locations during the week of February 27-March 3, 2023. All repairs done during normal business hours unless otherwise noted.

Achen-Gardner Construction
Achen-Gardner will perform miscellaneous sewer repairs at the following locations:

- 6712 N. Calle Padre Felipe: February 27 – March 3
- 6661 N. Skyway Dr: February 27 – March 3
- 7355 N. La Oesta Ave.: February 27 – March 1
- 6808 N. Green Mountain Pl: February 27
- 3100 E. Skyline Dr: February 27
- 6730 N. Campbell Ave.: February 27, March 3
- 2300 E. Miraval Primero: February 27
- 6600 N. Casa Grande Hwy: February 27 – March 3
- 6400 N. Casa Grande Hwy: February 27 – March 3
- 4000 W. Orange Grove Road: February 27 – March 3
- 3900 W. Orange Grove Road: February 27 – March 3
- 1909 E. Duval Vista: March 1 – March 3
- 3257 S. Campbell Ave.: February 27 – March 2

Borderland Construction Company
Borderland will perform miscellaneous sewer repairs around Drexel Manor Stravenue, including Felix Blvd. to the north, Drexel Road to the east and Benson Highway to the south. There will be small detours set up, but traffic will not be interrupted. Work began December 10 and is scheduled to continue through April 28, 2023.

Ellison-Mills Construction LLC
Ellison-Mills will perform miscellaneous sewer repairs at the following locations:

- 9722 E. Laurel Ridge Dr: March 1 – March 3
- 1830 S. Sunburst Dr: February 27
- 9871 E. Skyview Dr: February 28
- 6940 E. Malvern St.: March 2
- 245 S. Langley Ave.: March 3

Construction equipment, work crews and flaggers will be on site at the various locations. All drivers should slow down, heed signage and exercise caution when navigating through construction zones. Construction times are approximate and are subject to change if unforeseen conditions or inclement weather cause delays or postponements.