From: Town Of SouthboroughThere will be crane crews and buckets crews working throughout Town to remove trees on various streets as secured with the tree contractor. Please be advised that the DPW has coordinated with the schools to ensure bus routes would not be impacted and times were selected to be cognizant of high-traffic hours. The dates are below:
1/17/23 – Crane crew
1/19/23 – Crane crew
1/26/23 – Bucket crew
2/9/23 – Crane crew
2/21/23 – Crane crew
2/22/23 – Crane crew
2/23/23 – Crane crew
Week of 1/16 - Gilmore Rd and Oregon Rd should be complete.
Week of 2/20 - Work will be done on Flagg Road and Breakneck Hill during school vacation week to avoid impacting bus routes and motorists